Kanban

Also known as: Kanban card · Kanban systemLean Glossary · Waste & Flow

Definition

Kanban is a Lean scheduling tool that controls production and material flow with signals, usually cards or empty bins. A process only produces or delivers when it receives a Kanban signal from the next process, which creates a pull system and caps the stock between steps.

Where Kanban comes from

Kanban is Japanese for “signboard” or “card”. Taiichi Ohno developed the Kanban system at Toyota as the tool that makes Just-in-Time work on the shop floor. Like a supermarket shelf that is refilled only with what customers have taken, a Kanban loop replaces only what the next process has used.

Each card names the part, the quantity, the supplying process and the destination. Because the number of cards in a loop is fixed, the stock in that loop can never grow beyond the number of cards times the container quantity. In software and office teams, Kanban also stands for a visual board that limits work in progress; it is based on the same pull idea.

Types of Kanban

  • Withdrawal Kanban (also called move or transport Kanban): authorises moving parts from a supermarket to the process that uses them.
  • Production Kanban: authorises a process to make a set quantity to replace what was taken.
  • Supplier Kanban: triggers a delivery from an external supplier.
  • Two-bin system: the simplest form. When the first bin is empty, it goes back as the refill signal while work continues from the second bin.

How a Kanban loop works

  1. ConsumeThe assembly station takes parts from a full bin; the Kanban card stays with the bin.
  2. SignalWhen the bin is empty, the card goes to a Kanban post, or the empty bin itself goes back.
  3. ReplenishThe supplying process or the route train picks up the signal and produces or brings exactly that quantity, no more.
  4. ReturnThe full bin with its card goes back to the station, and the loop starts again.

A common way to size a loop: number of cards = daily demand × replenishment lead time in days × (1 + safety factor) ÷ quantity per container, rounded up. For a daily demand of 400 parts, a lead time of half a day, a safety factor of 0.1 and 50 parts per bin: 400 × 0.5 × 1.1 ÷ 50 = 4.4, so 5 cards. Teams then remove cards step by step to lower stock and expose problems.

Common Kanban mistakes

  • Too many cards: the loop works, but stock hides the problems it should reveal.
  • Ignoring the rules: producing without a card or moving parts without a signal breaks the pull.
  • Lost cards: without regular checks, cards disappear and the loop runs dry.
  • Introducing Kanban on an unstable process with long changeovers and frequent breakdowns. Stabilise first, for example with SMED, then pull.

Go deeper

Kanban: questions and answers.

What is the difference between Kanban in production and Kanban in software?

In production, Kanban cards or bins control the replenishment of parts between processes. In software and office teams, a Kanban board visualises tasks and limits work in progress. Both follow the same pull principle.

How many Kanban cards do you need?

A common formula is daily demand times replenishment lead time times one plus a safety factor, divided by the container quantity and rounded up. Start with that number and remove cards over time to reduce stock and expose problems.

What is a two-bin Kanban?

Two bins of the same part sit at the workplace. When the first is empty, it goes back as the refill signal while the operator works from the second bin.