The short answer
SMED (single-minute exchange of die) cuts changeover time by doing as much of the changeover as possible while the machine is still running, then simplifying what is left:
1Separate
Film one changeover and mark every step: internal (the machine must stand still) or external (it could still run).
Internal vs external2Convert
Do external work before the stop and turn internal steps into external ones: the next die is preset and waiting at the machine.
Steps 1–43Streamline and standardise
Quick clamps, fixed positions, no trial adjustments, and a written sequence that every shift is trained in.
Steps 5–7
Basics
What SMED is and why changeover time matters.
SMED stands for single-minute exchange of die: a method for changing a machine, line or cell over from one product to the next in as little time as possible. “Single-minute” does not mean one minute. It means a single-digit number of minutes, so under ten (Lean Lexicon, Lean Enterprise Institute). You will also hear quick changeover or setup reduction.
According to the Lean Enterprise Institute, changeover time runs from the last piece of the old run to the first good piece of the new one (Lean Lexicon, LEI). So trial parts, measuring and adjusting count, not just the swap of the tool.
Why changeover time matters:
Smaller batches
A one-hour changeover pushes people to run big batches to spread it. A ten-minute changeover makes it economical to build what customers ordered this week, with less stock and shorter lead times.
Flexibility
Rush orders and a wide variant mix stop being a disruption. Levelling the mix, known as heijunka, only works with short changeovers.
Capacity
While a machine is changed over, it produces nothing. Shorter changeovers raise its availability and with it the OEE, often before anyone has to buy a new machine.
The core idea
Internal vs external setup.
Everything else in SMED builds on one distinction. Sort every step of a changeover into one of two groups:
Internal setup
Only possible while the machine stands still
- Remove the old die, insert the new one
- Change format parts or fixtures
- Set, adjust and run trial parts
- Check the first part
External setup
Possible while the machine still runs
- Fetch the next die and bring it to the machine
- Preheat, preset or pre-assemble
- Prepare tools, material, program and papers
- Clean and store the old die after the restart

The question for every step: could this be done while the machine is still producing? If yes, it is external, even if today it happens during the stop. In a first observation, many steps done during the stop turn out to be external: fetching the die, searching for a spanner, waiting for the crane. Moving them costs almost nothing, so start there.
Analogy
What a pit stop teaches about changeovers.
A Formula 1 pit stop is the changeover everybody has seen on television. It is fast not because the crew rushes, but because it applies the SMED principles:
- 1
External work is done before the car arrives
New tyres, tools and people are in position and checked before the car enters the pit lane. Nothing is fetched during the stop.
- 2
Internal work runs in parallel
Each wheel has its own crew, so the stop lasts as long as one wheel change, not four in a row.
- 3
Fastening without adjusting
One centre nut per wheel, a powered wheel gun and fixed positions: nothing is lined up by trial and error.
- 4
The sequence is standard and rehearsed
Every person knows their task and its order, and the crew practises until the sequence is routine.
Your setters will not train like a racing team, and they do not need to. But the four questions carry straight over to any machine: what can be ready before the stop, who can work in parallel, what can be fixed once instead of adjusted every time, and is the sequence written down and practised?
SMED steps
SMED in 7 steps.
Shingo’s two insights become seven practical steps. Each card has a quick check and an example from one press changeover, which the worked example below adds up. The example figures are illustrations: put in your own.
Understand the current changeover
Steps 1–3: film, list, separate
1Film and time the current changeover
Choose one machine with frequent, long changeovers. Film a complete changeover, with the consent of the people filmed, and time it. Film the people, not just the machine: walking and searching are where the time goes.
Quick check
Example
2List every step
Watch the video with the crew and write down each step: what happens, who does it, start and end time, walking distance. Small steps count: “look for the 19 mm spanner” is a step. Our free SMED worksheet has the columns.
Quick check
Example
3Separate internal and external steps
Mark every step I (the machine must stand still) or E (it could still run). Then do all E steps before the stop or after the restart. This needs no investment, only planning.
Quick check
Example
Shorten the changeover
Steps 4–6: convert, streamline
4Convert internal steps into external ones
Change how the work is done, so that more of it can happen while the machine runs: preheat moulds, preset tools on a second fixture, pre-assemble parts, bring the next die to the right height before the stop.
Quick check
Example
5Streamline the internal steps
Shorten what must happen during the stop: quick clamps instead of bolts, one-turn fastenings, locating pins and standard heights instead of measuring, two people in parallel, and fixed settings so the first part is good.
Quick check
Example
6Streamline the external steps
External work still costs labour and can delay the start. A changeover cart, a shadow board and a fixed place for every die near the machine stop the searching. 5S makes it visible when something is missing.
Quick check
Example
Make it stick
Step 7: standardise and train
7Standardise and train
Write the new sequence as standard work with photos, who does what and the target time. Train every shift, keep timing the changeovers and display the times. Then start again: the next round finds new steps.
Quick check
Example
Worked example
A worked SMED example: from 52 to 14 minutes.
The same press changeover, step by step. The table shows how the stop shrinks, while some of the work moves to the time before or after the stop, when the press is running. Example figures are illustrations: put in your own.
52 min
stop per changeover before SMED
14 min
stop per changeover after SMED
−73 %
machine downtime per changeover
6.3 h
production time freed per week at 10 changeovers
| Step | Stop before | Stop after | What changed (SMED step) |
|---|---|---|---|
| Fetch die, clamps and material | 9 min | 0 min | Done while the press runs (step 3) |
| Search for tools | 9 min | 0 min | Gathered before the stop, then a shadow board on the changeover cart (steps 3 and 6) |
| Wait for the crane | 6 min | 0 min | Next die waits preset on a trolley at table height (step 4) |
| Unclamp and remove the old die | 8 min | 3 min | Quick clamps instead of bolts (step 5) |
| Insert, position and clamp the new die | 10 min | 6 min | Centring pins, standard height, two people in parallel (step 5) |
| Adjust and run trial parts | 8 min | 5 min | Settings stored per part number, marked end positions (step 5) |
| Clean the old die and take it to the store | 2 min | 0 min | After the restart (step 3) |
| Total machine stop | 52 min | 14 min | −38 minutes per changeover |
Notice where the minutes came from: 26 of the 38 minutes came from steps 3 and 4, from organisation rather than engineering. With ten changeovers a week, 38 minutes saved are more than six hours of extra machine time every week. What that is worth, and how you use it, is the job of the calculator below.
Calculator
Changeover savings calculator.
Put in your own figures. The example values are those of the press above. The calculator shows the machine and crew time freed per year, what it is worth and, as an alternative, how much smaller your batches could be in the same changeover time.
Result
- Machine time freed per year
- 291 h
- Value per year
- €43,700
- Saved per changeover
- 38 min−73 %
- Machine time freed per week
- 6.3 h
- Crew hours freed per year
- 583 h
Or: smaller batches
In today’s changeover time of 8.7 h a week you could change over 37 times instead of 10. At the same demand, each batch would be about 27 % of today’s size.
The value is only real if you use the time: more output on a bottleneck, less overtime, or more frequent changeovers and less stock.
Hours freed = changeovers per week × minutes saved × weeks ÷ 60. Value = hours freed × cost of one machine hour. Crew hours = hours freed × crew. Example values from the worked example; runs in your browser, nothing is sent or stored.
Decide before the workshop how the freed time will be used, and tell the crew. People who fear that a faster changeover costs a colleague’s job will not find the hidden minutes. More output on a bottleneck, less overtime or more frequent changeovers with less stock are all good answers. To check the effect on your key figures, use the OEE calculator.
Template
Changeover checklist to copy.
Use it to prepare every changeover while the machine still runs, and to check the restart. Copy it into your notes or print it for the changeover cart, and fill in the [brackets].
Checklist to copy
Changeover checklist
CHANGEOVER CHECKLIST: [machine], [from part] to [to part]
Planned start: [date, time] · Crew: [names] · Target stop time: [minutes]
Before the stop, while the machine still runs:
Next die or tool checked, cleaned and preset: [tool number]
Die, clamps and material on the changeover cart at the machine
Tools complete on the shadow board, nothing missing
Settings and program for [part number] ready
Crane, forklift or helper booked for [time], if still needed
Gauges and first-part inspection sheet at the machine
Crew briefed: who does which steps, in which order
During the stop, internal steps only:
Time of the last good part noted: [time]
Steps worked in the standard sequence, in parallel where defined
Settings taken from the standard, no trial-and-error adjustment
First good part approved: [time]
After the restart:
Old die cleaned, checked and returned to its place
Cart and shadow board complete for the next changeover
Changeover time written on the board at the machine: [minutes]
Problems and ideas noted for the next SMED round: [notes]
SMED training
SMED training: how to train teams.
SMED is easy to explain and hard to see in your own changeover: people have done it the same way for years. Training works best in three moves: practise on a neutral example, apply it to one real changeover, then keep the times visible.
1 · Practise
Play a changeover first
- A Lean game round with a changeover, before anyone looks at their own machine
- Separate internal and external steps on the neutral example
- Change the sequence, play again and compare the times
2 · Apply
One real changeover
- Film a real changeover with the crew’s consent
- List the steps on the SMED worksheet
- Mark internal and external, agree the first three changes
3 · Sustain
Keep the times visible
- Write every changeover time on a board at the machine
- Review the standard after the first month
- Next machine, next SMED round

In round 5 of the LeanActivity Online Game, the team runs a SMED workshop at station 1, where changing between the Light and Pro screwdriver takes 20 seconds. With a shadow board and then a one-touch slide, the changeover drops to 1 second. Changeover time is one of the 8 KPIs the team sees after every shift, so the effect shows in the next one.
With the physical Factory Game, the SMED game exercise has a walkthrough video and the free worksheet: watch the changeover, map every step, then redesign it together. For a wider programme, see Lean training.
Common mistakes
7 common SMED mistakes.
Buying technology first
Quick clamps and new tooling come after separating internal and external work, which costs almost nothing.
Stopping the clock at the tool swap
Changeover time runs until the first good part. Trial parts and adjustments are often the biggest block.
Analysing without the operators
The people who do the changeover know where the time goes, and they are the ones who will run the new standard.
One heroic changeover
A record during the workshop proves little. What counts is the average on every shift a month later.
No standard, no training
Without a written sequence, each shift does it its own way and the time drifts back.
Bigger batches with the time saved
If the freed time only goes into longer runs, stock and lead time stay as they were. Use part of it to change over more often.
Cutting corners on safety and quality
A fast changeover with a skipped lock-out or no first-part check is not an improvement.
Short changeovers pay off fully when the line also flows: see line balancing for spreading the work evenly across stations, and one-piece flow for where small batches lead.
LeanActivity
Practise quick changeover in a game first.
Experimenting on a real machine is expensive: every trial costs production time, and the crew defends the way it has always worked. In a game, a team can watch a changeover, take it apart into steps, change it and see the new time in the next round, within minutes.
Afterwards, ask: “Which of these steps would we find at our own machine?” Then take the question, a phone and the worksheet to the gemba.

Browser · 1–20 players
LeanActivity Online Game
A 3D factory in the browser: 12 rounds, 5 shifts and 7 improvement workshops in teams of 5, led by a moderator.
See the Online Game

Tabletop kit · 6–16 players
LeanActivity Factory Game
The physical Lean factory on the table: figures, parts and stations for workshops in the training room.
See the Factory Game
The Online Game demo runs in the browser, no installation.
FAQ
SMED: common questions.
What is SMED?
SMED, short for single-minute exchange of die, is a Lean method for reducing changeover time: the time from the last good part of one product to the first good part of the next. Its core idea is to do as much of the changeover as possible while the machine is still running, and to simplify the rest.
What does single-minute exchange of die mean?
Single-minute means a single-digit number of minutes, so a changeover of less than ten minutes, not one minute. Exchange of die refers to changing the die of a press, where the method started, but SMED applies to any changeover of a machine, line or cell.
Who developed SMED?
SMED was developed by the Japanese industrial engineer Shigeo Shingo. The Lean Enterprise Institute dates his key insights on setup reduction to the 1950s and 1960s. His book A Revolution in Manufacturing: The SMED System appeared in English in 1985, and its publisher describes him as the engineer who developed SMED for Toyota.
What is the difference between internal and external setup?
Internal setup can only be done while the machine is stopped, such as inserting a new die. External setup can be done while the machine is still running, such as bringing the next die to the machine or preheating it. SMED moves as much work as possible from internal to external.
What are the steps of SMED?
A practical sequence has seven steps: film and time the current changeover, list every step, separate internal and external steps, convert internal steps into external ones, streamline the remaining internal steps, streamline the external steps, and finally standardise the new sequence and train every shift.
What is an example of SMED?
In the illustration on this page, a press changeover takes 52 minutes. Fetching the die and tools before the stop, keeping the next die preset on a trolley at table height, quick clamps, centring pins and two people working in parallel cut the stop to 14 minutes, so the press gains 38 minutes of production time per changeover.
How do you calculate the savings of a quicker changeover?
Multiply the minutes saved per changeover by the changeovers per week and the working weeks per year, then divide by 60 for the hours freed. Multiply the hours by the cost of one machine hour to value them, and by the crew size for the labour hours. To see how much smaller batches could be, divide today’s weekly changeover time by the new changeover time.
How do you run SMED training?
Start with a hands-on exercise on a neutral example, so the team learns to see internal and external steps without defending its own routine. Then apply the method to one real changeover: film it, list the steps, separate and shorten them, and write the new standard. Afterwards, keep the changeover times visible at the machine.
What is a SMED game?
A SMED game lets a team practise quick changeover in a simulation before it works on a real machine, where every trial costs production time. In round 5 of the LeanActivity Online Game the team cuts the changeover at station 1 from 20 seconds to 1, and for the physical Factory Game there is a SMED exercise with a walkthrough video and a free worksheet.