OEE (Overall Equipment Effectiveness) measures how much of the planned production time a machine or line turns into good parts. It is calculated as Availability × Performance × Quality; an OEE of 100% means only good parts, at the ideal speed, with no stops.
What OEE measures
OEE was made popular by Seiichi Nakajima as part of Total Productive Maintenance (TPM). It combines three kinds of loss in one number:
- Availability = run time ÷ planned production time. It captures stops such as breakdowns, changeovers and waiting for material.
- Performance = (ideal cycle time × total count) ÷ run time. It captures slow cycles and short stops.
- Quality = good count ÷ total count. It captures scrap and parts that need rework.
OEE = Availability × Performance × Quality. The same result comes out of a shorter formula: OEE = (good count × ideal cycle time) ÷ planned production time.
How to calculate OEE: a worked example
- Planned production timeA shift lasts 480 minutes with a 30-minute break, so the planned production time is 450 minutes.
- AvailabilityThe machine stops for 45 minutes in total (a breakdown and a changeover), so the run time is 405 minutes. Availability = 405 ÷ 450 = 90%.
- PerformanceThe ideal cycle time is 1 minute per part, and the machine makes 360 parts. Performance = (1 × 360) ÷ 405 = 88.9%.
- Quality18 of the 360 parts are scrap, so 342 are good. Quality = 342 ÷ 360 = 95%.
- OEEOEE = 0.90 × 0.889 × 0.95 = 76%. Check: 342 good parts × 1 minute ÷ 450 minutes = 76%.
The six big losses
TPM groups the losses behind OEE into six categories, two for each factor:
- Availability: equipment failures, and setup and adjustments (changeovers).
- Performance: idling and minor stops, and reduced speed.
- Quality: defects and rework during production, and start-up losses until the process runs stably.
Tips for improving OEE
- Record losses by cause, not only the final percentage: the number alone does not tell you what to fix.
- Attack changeover time with SMED, and breakdowns with autonomous maintenance and 5S.
- Use the true ideal cycle time, not a comfortable standard, or Performance will look better than it is.
- Compare a machine with itself over time rather than with other plants, because definitions of planned time differ.
- Focus on the bottleneck. More output from a machine that is not the bottleneck only builds stock in front of the next step.
Go deeper
OEE: questions and answers.
What is a good OEE?
There is no universal target, because OEE depends on the process and on how planned production time is defined. The most useful comparison is the trend of the same machine over time and the size of each individual loss.
What is the difference between OEE and TEEP?
OEE refers to planned production time. TEEP (Total Effective Equipment Performance) refers to all calendar time, so it also shows how much time is not scheduled at all.
Can OEE be higher than 100%?
No. If the calculation gives more than 100%, the ideal cycle time is set too slow or the counts are wrong. Check the ideal cycle time first.